Gateway 2 Preparation Template

Document index and readiness template for Gateway 2 (pre-construction) submissions under SI 2023/909 — design intent, control plans, competence, golden thread, and portal-day readiness before HRB building work starts.

Last reviewed 26 July 2026PDF + Excel · 14 pages
Full educational guide

What the law requires

Gateway 2 is the pre-construction hard stop for England higher-risk buildings under SI 2023/909: building work must not start until the BSR has approved the design intent package. Competence and dutyholder arrangements sit alongside in SI 2023/911. Use this index to assemble evidence; cross-check GOV.UK building-control approval guidance before you file.

Key clocks

  • Hard stop

    No commencement of building work until Gateway 2 approval is in place (SI 2023/909).

  • Levy (from 1 Oct 2026)

    Consider SI 2025/1236 applicability for relevant applications — evidence fields only, not a liability calculator.

Operating checklist

Gateway 2 is the pre-construction hard stop for England higher-risk buildings under SI 2023/909. Use this template to assemble the design intent and management package the BSR expects before you apply for approval to commence building work. Cross-check against current GOV.UK building-control approval guidance before filing — software prepares; the duty-holder files on the official portal.

Submission administration

  • BSR application reference and project identifiers
  • Named submission owner and competent signatory
  • List of co-submitters / duty holders included in the pack
  • Version register for all documents in the submission
  • Client / PD / PC appointment letters attached or linked
  • Correspondence log for pre-application BSR engagement (if any)

Duty holders & competence (SI 2023/911)

  • Principal Designer and Principal Contractor competence evidence available
  • Designer / contractor competence declarations current for safety-critical packages
  • Limitations and specialist appointments recorded (fire, structure, façades)
  • Competence remains appointing-party judgement — presence of certificates ≠ accreditation by the platform

Design intent — fire safety

  • Fire strategy report (current issue)
  • Fire risk assessment (construction phase)
  • Means of warning and escape strategy
  • Compartmentation and fire-stopping schedule
  • External wall system and cladding fire performance evidence
  • Smoke control and ventilation design
  • Fire service access and facilities statement

Design intent — structure

  • Structural concept and stability strategy
  • Design calculations summary
  • Key structural risk assumptions and mitigation
  • Material specifications for safety-critical elements
  • Geotechnical / foundation assumptions affecting structural safety

Design intent — building services

  • MEP layouts affecting fire or structural safety
  • Sprinkler / suppression design (if applicable)
  • Emergency lighting and power resilience
  • Lift and evacuation lift provisions (if applicable)
  • Life-safety systems interfaces schedule (cause-and-effect where relevant)

Management & control plans

  • Construction control plan
  • Change control procedure (SI 2023/909) — how safety-critical changes are captured and re-submitted
  • Quality assurance plan for safety-critical works
  • Inspection and test plan (ITP) for regulated systems
  • Mandatory occurrence arrangements for the construction phase understood (works-phase duties distinct from occupied MOR under SI 2023/907 reg.6)

Golden thread at Gateway 2 (SI 2023/909 Part 4)

  • Information requirements matrix (what, when, who)
  • Naming convention and folder structure
  • Evidence of digital or physical record-keeping approach
  • Plan for as-built updates through construction into Gateway 3 / s.76 handover
  • Plan for continuity into occupied SI 2024/41 Schedule 1 keep-list

Levy & commercial awareness (ceiling)

  • Building Safety Levy applicability considered for applications on/after 1 Oct 2026 (SI 2025/1236)
  • Evidence fields for liability / amount / payment / receipt planned if in scope — not a liability calculator

Readiness sign-off & portal day

  • Principal Designer review complete
  • Principal Contractor construction readiness confirmed
  • Client / developer approval to submit
  • Outstanding conditions from Gateway 1 closed or tracked
  • Portal-day pack ready (checklist status, document index, HSE / BSR reference reminder)
  • No assumption of live HSE / BSR e-file from the platform

Prefer narrative reading?

Educational guides are the indexed deep-read for this topic. This checklist stays printable and out of commercial search competition.

BSR expectations evolve. Cross-check this index against the latest GOV.UK building-control approval guidance for higher-risk buildings and SI 2023/909 before submission. Companion guide: threadsovereign.co.uk/gateways. Reviewed 26 July 2026.

© 2026 Threadsovereign Ltd. Provided for general guidance only — not legal advice.